TEXO managed the project’s survey data to help ensure a smooth construction process and was on hand to provide further detailed advice, accurate measurement and verification when required.
Throughout the construction, TEXO site engineers were able to provide:
With such close proximity to the active network rail lines that border the site, the TEXO team needed to be able to deliver millimetre-level monitoring during the construction phase by establishing an accurate control network and dense monitoring target network on site.
By using a state-of-the-art 1” total station and multiple observation periods (conducted pre-piling to establish a baseline value set / multiple time-periods throughout the active piling and finally a post-piling observation) to determine the level of movement was within Network Rail’s acceptable tolerance levels.
Daily monitoring reports were sent to the client along with automated trigger-level reporting, enabling real-time communication of any measurements.